Question reference: S3W-39646

  • Asked by: John Farquhar Munro, MSP for Ross, Skye and Inverness West, Scottish Liberal Democrats
  • Date lodged: 14 February 2011
  • Current status: Answered by Keith Brown on 16 March 2011

Question

To ask the Scottish Executive what further steps are needed for the reopening of Conon Bridge railway station; how the reopening process will be managed, and what the timescale is.


Answer

The steps required to be undertaken to enable Conon Bridge Station to be re-opened are:

Network Rail Process

Timescales

Detailed Design Work

Up to 6 months

Procurement Stage

At least 6 to 9 months

Construction and Commission

Up to 12 months

 

It is anticipated (subject to funding being made available) that Network Rail would take over the scheme as project manager to enable the procurement and construction work to take place.