Question reference: S2W-31923
- Asked by: Carolyn Leckie, MSP for Central Scotland, Scottish Socialist Party
- Date lodged: 21 February 2007
-
Current status: Answered by Tavish Scott on 5 March 2007
Question
To ask the Scottish Executive, further to the answer to question S2W-31693 by Tavish Scott on 19 February 2007, how the public and the Highland Regional Council were informed of the length of toll period represented by the arrangement referred to in the answer.
Answer
The anticipated length of thetoll period was set out in the Skye Bridge Assignation Statement,which was made available for public inspection in October and November 1991.